74°
Baton Rouge, Louisiana
3 Day Outlook
Mon
83°
59°
20%
Tue
81°
62°
10%
Wed
82°
65°
20%

Latest Weather Blog

Follow our weather team on social media

I-10 widening project falls behind schedule

3 years ago Tuesday, May 03, 2011 12:53:27 PM CDT May 03, 2011 Tuesday, May 03 2011 May 3, 2011 in News
Source: WBRZ

BATON ROUGE- The I-10 widening project between the 10/12 split and Siegen Lane is about a year behind schedule, according to State Transportation Leaders.

"There were some initial plan changes in the beginning," Jodi Conachen with DOTD said.  "We have some issues with insufficient resources being dedicated."

The project was scheduled to be finished at the end of this year.  However, it is now set for completion in the fall of 2012. 

News 2 has learned, the contractor, Austin Bridge Inc. received a disqualification letter from DOTD last week.  All sides are scheduled to meet about the issue Thursday to talk about moving forward. 

The same contractor working on the I-10 project also was disqualified from a project being done in Shreveport.  According to DOTD, the disqualification came after the contractor fell behind schedule there too. 

"They can't bid on any projects until the disqualification is lifted," Conachen said. "If they were to dedicate sufficient resources to move the project along, that would lift the disqualification."

News 2 tried to reach the contractor about this issue, but several phone calls were not returned.  DOTD leaders say they can be fined up to $15,000 per day after the deadline for completion.  Right now, the fine stands at approximately $4.5 million.

A different contractor is widening I-10 between Siegen Lane and Highland Road.  That project is on schedule and will open in early 2013.

More News

comments powered by Disqus

Desktop News

Click to open Continuous News in a sidebar that updates in real-time.
5 Days
Radar
Today
74°
60°
Mon
Partly Cloudy
83°
59°
Tue
Partly Cloudy
81°
62°
Wed
Partly Cloudy
82°
65°
Thu
Partly Cloudy
86°
68°